This was the first hotel purchased in the UK by one of Legacy Hotels clients. Very quickly they decided to carry out two trial rooms, one was a full bathroom and bedroom refurbishment, the other was a considered schedule, taking into account what items could be kept and designed around. An example of this was keeping the existing case goods, re-polishing them and adding back painted glass tops. The trial rooms here deemed a success and the costs we produced made them economically viable.
As part of the roll out programme we undertook a full survey of each room and produced a works schedule accordingly. Due to the nature of the works a contractor, who we had worked with previously, was chosen and the contract was negotiated as time was of the essence.